Vegas Loop central station with Tesla vehicles 라스베이거스 루프
Tesla & SpaceX

Vegas Loop, the annex stations that double the count without new tunnels

🇰🇷 한국어로 보기 →

Vegas Loop will grow from 14 stations to 28 by the end of this year, The Boring Company said in a post on X on 14 September. The same post carried two job listings, one for a Loop driver and one for a senior Loop operations manager.

Doubling a transit system inside three and a half months normally implies an enormous amount of digging. This time it does not. On the company own project page, the tunnel count over that same period goes from 14 to 15.

One tunnel. The rest of the doubling comes from stations attached to holes that are already in the ground, and most of them sit in a category the company calls an annex station: four today, fifteen by year end.

That gap between the two numbers is the part worth reading closely, because it describes how the whole system is meant to grow from here.

Vegas Loop underground station with tunnel portals
An underground Loop station lit in blue, with an arched tunnel opening on each side and a display screen on the far wall. The stations opening this year attach to tunnels like these. Photo: Steve Jurvetson, CC BY 2.0

Vegas Loop, and the one number that is not doubling

The Boring Company publishes a short table titled By the Numbers on its Vegas Loop page. Read on 15 September, it sets today against the end of 2026 across eight rows.

Tunnels go from 14 to 15. Subsurface stations stay at 2. Surface stations go from 8 to 11. Annex stations go from 4 to 15.

Add those up and the total moves from 14 to 28. Emergency egress points go from 12 to 14, cross-passages stay at 6, and knockout shafts go from 9 to 10.

The structural and safety rows barely move, which is the clearest sign that the underground layout is close to fixed. What changes is the number of places a passenger can get in and out.

The live list today runs through the convention campus and the resort corridor: LVCC South, West, Central, Central Plaza and Riviera, then Resorts World, Encore, Westgate, Fontainebleau, Sahara and Turnberry Towers, plus Airport T1 and T3.

The opening-soon list names Virgin, Hughes Center, 4744 Paradise by UNLV, the Renaissance Hotel, Hyatt Place, the Stirling Club and The Collective, then simply adds seven more without naming them.

The tunnels underneath all of this are short. The convention centre pair runs 9,030 feet, the Westgate Connector 3,945 feet, the Resorts World Connector 3,325 feet and the Encore Connector 2,320 feet.

The system has carried more than four million passengers so far, with rides between two and eight minutes. Boring Company executive Mike Baier said in July that it moves around 40,000 passengers on busy convention days.

Vegas Loop station and tunnel counts today and at the end of 2026
Every row that involves digging is flat or nearly flat. The doubling sits almost entirely in the annex station row. Source: The Boring Company project page, read 15 September 2026.

Vegas Loop economics, why a doorway costs less than a tunnel

The economics are easiest to see through the first segment the company built. The LVCC Loop is three stations on 1.7 miles of tunnel, delivered in roughly a year for about 47 million dollars on a firm fixed price.

The digging happened underneath conventions drawing more than 100,000 attendees, with no road closures. It replaced a 45-minute cross-campus walk with a ride of about two minutes.

That segment has since demonstrated peak throughput above 4,500 passengers an hour and more than 32,000 in a day. None of that capacity came from laying more tunnel after it opened.

This is the logic behind the annex station. The tunnel is the slow, expensive, heavily permitted item. A station on a tunnel that already runs past a building is a shaft, a platform and a queue line.

So the marginal cost of the twenty-eighth station looks nothing like the marginal cost of the first, and the number of useful destinations grows faster than the mileage does.

The current work makes the pattern visible. Just over two miles of dual tunnel under Paradise Road, from Westgate to a planned station at 4744 Paradise Road, is opening in stages over the coming weeks, Las Vegas Convention and Visitors Authority chief executive Steve Hill told the Las Vegas Review-Journal.

Seven of the stations due this year sit along that one stretch: 4744 Paradise, Virgin, the former Gordon Biersch site, the Renaissance Hotel, Hyatt Place, the Stirling Club and The Collective.

Throughput in a system like this comes from vehicles and doors rather than track, which is why the fleet choice matters. The Loop runs on Teslas, and the one recurring cost the model still carries is the person behind the wheel, which is what this week job listings are about.

Tesla is unusually well placed to take that cost out, and not because of any claim about public roads. A fixed, mapped, grade-separated tunnel with no pedestrians, no weather and no oncoming traffic is about as favourable a setting as autonomy is ever offered, and Tesla is the only carmaker supplying a fleet into one at this scale. The same argument runs through its Cybercab design, which was drawn around the fleet rather than the driver.

The company has already used the same approach inside a Tesla factory. The Cybertunnel at Giga Texas replaced a 12-minute surface drive across an eight-lane state highway with a 60-second underground link, dug by the Prufrock-3 machine.

Tesla vehicles at a Las Vegas Loop surface station
Teslas queued at a street-level Loop stop, with the Sphere visible behind. No tunnel is visible in this photo; the portal sits below and behind the camera. Photo: Joseph Zadeh, CC BY-SA 4.0

What the company has not said yet

Boring Company did not name the stations beyond those already under construction that will open by year end, and did not say whether the hiring push implies a larger fleet alongside the new stops.

Entitlement and construction also move at different speeds. Clark County and the City of Las Vegas have approved 68 miles of tunnel and 123 stations, after the county added 19 more in August. Fourteen are running today.

The airport is the least settled part of the picture. The project page lists Airport T1 and Airport T3 among active stations and publishes a Harry Reid to convention centre trip at 4.9 miles, five minutes and 14 dollars.

Reporting from 14 September instead describes the airport link as a future stage with no estimated completion date, and describes the Paradise Road stations as built partly to speed rides toward Harry Reid before November Formula 1 race. The company has not reconciled the two descriptions publicly.

It also cautioned that schedules could shift, which is worth holding onto given the history. The station target has climbed from 69 across 65 miles in 2023 to roughly 93, then 104, then 123.

What is different this week is the noun the doubling attaches to. Earlier doublings were of stations approved on a county map. This one is of stations actually carrying passengers.

Public reaction in Las Vegas remains mixed. Fox5 found visitors who did not know the system was already running, a resident who welcomed anything that thins weekend traffic, and a California visitor who said he was not convinced. Nevada regulators have been similarly cautious with the robotaxi permits granted in the same county.

Meanwhile the template is being exported. Music City Loop in Nashville is under construction, and a Dubai Loop pilot of 6.4 kilometres and four stations linking the Dubai International Financial Centre to the Dubai Mall is under contract, backed in part by a 3 billion dollar Series D.

References

The Boring Company, Vegas Loop project page / Teslarati, 14 September 2026 / Fox5 Vegas, 14 September 2026 / Las Vegas Review-Journal, Road Warrior / The Boring Company, Tunnels

답글 남기기

이메일 주소는 공개되지 않습니다. 필수 필드는 *로 표시됩니다